2024年4月16日发(作者:)
工厂常见的英文缩写
ISO 国际标准化组织(ISO,International Organization for Stan-dardization缩写)。
OEM是英文Original Equipment Manufacturer的缩写,意思是原设备制造商
R&D (research&design) 研发
ODM,即Original design manufacture(原始设计商)
的缩写。
IQC incoming quality control
RD research development center
IPQC in process quality control
RD HQ research development center
head quarter
FQC final quality control
QA quality assurance
BOM bill of material
PVT product verification test产品验证测试
OQC outgoing quality control
PRP phase review process阶段检讨过程
QE quality engineering
PM project management
DCC document center control
PJE project engineer
ECN engineering change notice
PE product engineer
ECR engineering change request
NPI new product introduction
MRB material review bom
EOL end of life
QSA quality system audit
EN engineering notice
ATE automatic test equipment自动测试设备
EMI electromagnetic interference电磁干扰
EMC electromagnetic compatibility电磁兼容性
PCBA print circuit board assembly印刷电路板组装
EE electronic engineer(ing)
TTL technology transfer list
EDC electronic data center
SQA supplier quality assurance
ECO engineering change order
ORT ongoing reliability testing(可靠性测试)
DVT design verification test(设计验证测试)
QM quality manual
DOA dead on arrival
SW software
CAD/ID computer aided design /industrial
design
SOW standard of work
BIOS basic input /output system
AOI automatic optical inspection自动光学检测
MP mass production SCSI small computer system interface
CAR corrective action request纠正行动请求
AP
application program
MFG manufacturing
FPC flexible printed circuit board
ME mechanical engineer
NCR non conforming report
KBD keyboard
OBE out of box evaluation
IFR instant failure rate
IFIR instant failure incident rate即时故障发生率
PCR process change request
HW hardware
IPO internal purchase office
N/A No Action
IE industrial engineering
ESD electrostatic discharge静电放电
QPA quality process audit
SA software application
AFR annual failure rate
SO sales order
NTF no trouble found
MRP material requirement planning
CND can not duplicate
AVL approved vendor list
FAI first article inspection
FMEA failure mode effect analysis
CLCA closed loop corrective action
LRR line reject rate measured by DPPM
MQR monthly quality review
MTQ manufacturing ,test and quality
RCA root cause analysis
PFMEA process failure mode effect analysis
IQA internal quality audit内部质量审核
DPPM
defect parts per million
向定春 2010-9-3 Page 1 of 3
工厂常见的英文缩写
P/N Part Number 料号
SFIS Shop Floor Information System
L/N Lot Number 批号
QEM Quality engineering measurement
BGA Ball Grid Array
IC Integrated Circuit
QFP Quad Flat Pack
AOD Accept On Deviation 特采
UAI Use As It 特采
FPIR First Piece Inspection Report
EOS Elwctrical Over Stress
首件检查报告
TNB terminal notebook business
SMT Surface Mount Technology
PPM Percent Per Million 百万分之一
制程统计品管专类
SPC Statistical Process Control 统计制程管制
SQC Statistical Quality Control 统计品质管制
GRR Gauge Reproductiveness &
Repeatability量具之再制性及重测性判断量可靠与否
DIM Dimension 尺寸
DIA Diameter 直径
N Number 样品数
品质人员名称类
QC quality control 品质管理人员
FQC final quality control 终点品质管制人员
IPQC in process quality control 制程中
的品质管制人员
OQC output quality control 最终出货品质管制人员
IQC incoming quality control 进料品质管制人员
TQC total quality control 全面质量管理
POC passage quality control 段检
人员
QA quality assurance 质量保证人员
OQA output quality assurance 出货
质量保证人员
QE quality engineering 品质工程人员
其它品质术语类
QIT Quality Improvement Team 品质改善小组
ZD Zero Defect 零缺点
QI Quality Improvement 品质改善
QP Quality Policy 目标方针
TQM Total Quality Management 全面品质管理
RMA Return Material Audit 退料认可
7QCTools 7 Quality Control Tools 品管七大手法
ECN Engineering Change Notice
工程变更通知(供应商)
ECO Engineering Change Order
工程改动要求(客户)
PCN Process Change Notice 工序
改动通知
品质保证类
FAI first article inspection 新品首
件检查
FAA first article assurance 首件确认
CP capability index 能力指数
CPK capability process index 制程
能力参数
SSQA standardized supplier quality audit PMP Product Management Plan
合格供应商品质评估 生产管制计划
FMEA failure model effectiveness analysis SIP Standard Inspection Procedure
失效模式分析 制程检验标准程序
FQC运作类
AQLAcceptable Quality Level 运作类允收品质水准
S/S Sample size 抽样检验样本大小
ACC Accept 允收
REE Reject 拒收
CR Critical 极严重的
MAJ Major 主要的
MIN Minor 轻微的
Q/R/S Quality/Reliability/Service
品质/可靠度/服务
SOP Standard Operation Procedure 制造作业规范
IS Inspection Specification 成品检验规范
BOM Bill Of Material 物料清单
PS Package Specification 包装规范
SPEC Specification 规格
DWG Drawing 图面
系统文件类
ES Engineering Standard 工程标准
CGOO China General IWS
International Workman Standard 工艺标准
向定春 2010-9-3 Page 2 of 3
工厂常见的英文缩写
CHK Check 确认
ISO International Standard Organization
国际标准化组织 ASS'Y Assembly 装配,组装
GS General Specification 一般规格
部类
PMC Production & Material Control
生产和物料控制
T/P True Position 真位度
5WIH When, Where, Who, What, Why,
How to
6M Man, Machine, Material, Method,
PCC Product control center Measurement, Message
生产管制中心
4MTH Man, Material, Money, Method, Time,
PPC Production Plan Control
生产计划控制
MC Material Control 物料控制
DC Document Center 资料中心
QE Quality Engineering 品质工程(部)
QA Quality Assurance 品质保证(处)
QC Quality Control 品质管制(课)
PD Product Department 生产部
LAB Laboratory 实验室
IE Industrial Engineering 工业工程
R&D Research & Design 设计开发部
How 人力,物力,财务,技术,时间(资源)
SQA Strategy Quality Assurance 策略品质保证
DQA Design Quality Assurance设计品质保证
MQA Manufacture Quality Assurance
制造品质保证
SSQA Sales and service Quality Assurance
销售及服务品质保证
LRR Lot Reject Rate 批退率
SPS Switching power supply 电源箱
DT Desk Top 卧式(机箱)
MT Mini-Tower 立式(机箱)
DVD Digital Video Disk
VCD Video Compact Disk
LCD Liquid Crystal Display
CAD Computer Aided Design
CAM Computer Aided Manufacturing
CAE Computer Aided Engineering
PCB Printed Circuit Board 印刷电
路板
CAR Correction Action Report 改善报告
NG Not Good 不良
WDR Weekly Delivery Requirement 周出货要求
PPM Percent Per Million 百万分之一
生产类
PCs Pieces 个(根,块等)
PRS Pairs 双(对等)
CTN Carton 卡通箱
PAL Pallet/skid 栈板
PO Purchasing Order 采购订单
MO Manufacture Order 生产单
D/C Date Code 生产日期码
ID/C Identification Code (供应商)识别码
SWR Special Work Request 特殊工作需求
L/N Lot Number 批号
P/N Part Number 料号
OEM Original Equipment Manufacture TPM Total Production Maintenance
原设备制造 全面生产保养
PC Personal Computer 个人电脑
CPU Central Processing Unit 中央处理器
A.S.A.P As Soon As Possible 尽可能快的
E-MAIL Electrical-Mail 电子邮件
N/A Not Applicable 不适用
QTY Quantity 数量
I/O input/output 输入/输出
NG Not Good 不行,不合格
C=0 Critical=0 极严重不允许
APP Approve 核准,认可,承认
向定春 2010-9-3 Page 3 of 3
MRP Material Requirement Planning物料需计划
OS Operation System 作业系统
TBA To Be Assured 待定,定缺
发布者:admin,转转请注明出处:http://www.yc00.com/news/1713208012a2204226.html